Quality Control
Plan
A Quality
Control Plan will be required for all construction products covered
by the EU Construction Products Directive (89/106/EC) that are the
subject of attestation of conformity (AoC) procedures relating to
product certification or certification of factory production
control, i.e. AoC levels 1+, 1, 2+ and 2. The Quality Control Plan
should specify the particular production operations necessary to
ensure the continuing compliance of the certified product with the
requirements of the harmonized European Product Standard. The
document should be properly controlled and authorized for issue.
A copy of the
Quality Control Plan and the factory production control documents
should be submitted to the Notified (certification) Body for review.
This may not necessarily be the same organization as currently
provides quality management system certification to ISO 9000 to your
company. In the case of the CPD, the Notified (certification) Body
role within BSI is carried out by BSI Product Services, using BSI
Global Quality Services to perform the inspections of factories and
their FPC systems.
Once
implementation of the FPC system has been assessed and accepted (and
the relevant EC Certificate of Conformity issued), the Quality
Control Plan should be retained on file and any proposed amendments
should be submitted for clearance before being
implemented.
General
guidance for Quality Control Plan: The following provides general
guidance on the contents of a Quality Control Plan that is likely to
be acceptable in a majority of cases.
The operations
should be regarded as additional to those that would normally be
carried out under a quality system to ISO 9000. It is emphasized
that this envisages a standard situation that may not be applicable
in all circumstances.
A Quality
Control Plan must reflect the requirements of the relevant
harmonized European product standard, particularly the Annex Z
covering the provisions of CE marking and should include, but not be
limited to, the following:
·
Specific raw materials and/or component
specifications with the inspection and/or test criteria.
·
Details of the manufacturing process
identifying critical stages, the in-process inspection procedures,
limits of acceptance and rejection criteria. This should include,
where appropriate, a process flow chart of the manufacturing and
inspection stages.
·
Particular procedures for dealing with
non-conforming product e.g. disposal, identification, segregation,
corrective action.
·
Frequencies of tests on finished products and
the test methods to be used.
·
Details of the further testing of samples in
accordance with a prescribed test plan
·
Specific sampling requirements and related
procedures.
·
Cross-references to the quality management
system or FPC document.
·
Calibration of measuring equipment and
special equipment used in the manufacturing process.
·
Where appropriate, the particular marking
requirements of the product standard and the Directive.
·
Retention periods of records specific to the
product concerned.